Project Management
Esempio di domande di esame
1) You are assigned a project that
requires the manufacturing of medical equipment for one of your company’s
current clients. Your company has executed similar projects successfully in
the past. During which phase of the project would you consider referring to
previous project documents for the similar projects?
-
Scope
planning
-
Scope
verification
-
Scope
definition
-
Initiation
2) What tools and techniques are
typically used in the scope definition process?
-
Analysis of the product,
cost/benefit analysis estimates, identification of alternative
approaches, and expert judgment.
Work breakdown structure templates and decomposition of
deliverables into smaller, more manageable components.
Review of historical information, creation of project
constraints and assumptions, and cost/benefit analysis estimates
Project justification, work breakdown structure
templates, and identification of alternative approaches.
3)
You are employing Earned Value Management on your project. You wish to avoid
the subjective determination of performance as reported by the work package
owners in your weekly status meetings. The following table describes three
of your work packages:
|
Work Package |
Description of the Work
|
Estimated Duration
|
|
2.2.1 |
Create RFP for
subcomponent parts |
4 weeks |
|
2.2.3 |
Purchase
subcomponent parts |
2 weeks |
|
2.2.5 |
Assemble
subcomponent |
3 weeks |
Which of the
following methods of measuring earned value works BEST for work
package 2.2.1?
- Fixed formula
Weighted milestones
Percent complete
Equivalent completed units
The ______________ evaluation method
works BEST for work package 2.2.3.
- Fixed formula
- Weighted milestones
- Percent complete
- Equivalent completed units
4) Assurance that activities
throughout time have conformed to the organization’s requirements can be
accomplished through the use of:
- Status reports.
- Project stage gates.
- Benchmarking.
- Control charts.
5) You are the project manager on
a project that has met all deliverables on schedule and on budget. What
MUST be done to ensure all work was completed correctly and
satisfactorily?
- Perform product verification.
- Perform a procurement audit.
- Obtain formal acceptance from
the client.
- Obtain formal approval from the contracts manager.
6) Company A and Company B merge to create a new
organization, Company ABC. Both companies operated strategic business units
and employed full-time project managers. Although both companies were
composite matrix management organizations, their corporate and project
management cultures and organizational structures differed. Company A’s
project management organizations tailored their processes and tools to their
assigned strategic business units; Company B’s project management
organizations centralized the development of processes and tools for
corporate-wide adoption. The new organization, Company ABC, retained the
strategic business units, composite matrix management organization, and
full-time project managers. It has a single project organization that aligns
project managers with strategic units.
What kind of project management behavior
culture would MOST likely have developed at Company A?
- Isolated
- Fragmented
- Non-cooperative
- Competitive
Company ABC has separate headquarters in
the United States and the United Kingdom to oversee its North American and
European regions respectively. Which cultural characteristics are
MOST
likely to be evident
at the North American headquarters?
- Communicate formally and respect tradition.
- Focus on task
accomplishments and reward individualism.
- Value history, hierarchy, individualism and
loyalty.
-
Communicate indirectly and emphasis hard work and success.
(risposte corrette: 1D, 2A, 3BA, 4D, 5C, 6AB)